Mihai Ionescu-Balea, attorney-at-law
Since 28 February 2026, the US-Israel war on Iran has kept the Strait of Hormuz, the passage for about one fifth of the world’s oil before the war, in a state of near-permanent disruption. Last week, Brent traded at around USD 110-113 per barrel, close to a five-month high, amid new reported tanker attacks; drone attacks on ships have reached the Black Sea off the Romanian coast; and EU gas storage enters winter at historically low levels.
Romanian sites are already feeling it: key materials have become 15-30% more expensive since the start of the year, and bitumen rose by around 60% in March. On top of this, interest rates in Romania are the highest in the European Union, making the situation even worse. The question for every project is the same: who bears this risk? The answer comes first from the contract, then from the law, and, in practice, from how well each party has documented its position. This article sets out practical steps for contractors and employers.
1. First step: contract analysis
Under EPC and other lump-sum contracts, the contractor typically bears the price and time risk: a fixed price, a fixed completion date and limited scope for extensions of time (“EOT”) or additional payment. Design & build contracts tend to share risk more evenly. Before taking any position, map each contract (main contract, subcontracts, supply agreements) against four questions:
- Is there a price adjustment formula or indexation clause, and which indices does it use?
- Does the force majeure (or “Exceptional Events”) clause cover war, hostilities, blockades, sanctions or embargoes, and does it require performance to be “prevented” or merely “hindered”?
- What are the grounds for an EOT and the notice deadlines, and are they conditions precedent?
- When do liquidated damages (“LDs”) accrue, and when does the employer acquire a right to terminate?
The date of signature of the contract is also essential. A contract concluded after 28 February 2026 (or after Hormuz was first closed) was concluded against a known risk, which makes the arguments for force majeure or hardship discussed below less compelling.
2. Force majeure: a high bar and a short fuse
Under Article 1351 of the Romanian Civil Code, force majeure is an external, unforeseeable, absolutely invincible and unavoidable event. It applies by operation of law, even without a clause, and the parties may adjust it by contract. This differs from English and American law, where force majeure exists only if the contract provides for it, a point to keep in mind for contracts governed by foreign law, which are common in large projects.
Three recurring problems arise in practice:
- Cost is not impossibility. A price increase, however steep, does not prevent performance. Courts and tribunals construe force majeure narrowly: Romanian jurisprudence is very reticent about applying force majeure when a mere price spike occurs without rendering performance impossible.
- Foreseeability and causation. Force majeure is difficult to invoke for events that were foreseeable at signing, and the event must be the real cause of non-performance. For example, a slower transport route for the supply of materials to the site is a delay to manage, not an impossibility, and the party relying on the event must show it took reasonable mitigation steps.
- Notice. FIDIC 2017 requires notice within 14 days of the party becoming aware of the Exceptional Event (Sub-Clause 18.2); if notice is late, relief runs only from the date of notice. Under Article 1634 of the Romanian Civil Code, a debtor who relies on impossibility must notify the creditor within a reasonable time and bears the burden of proof.
Contractors should also verify whether their own suppliers have invoked force majeure upstream. If the subcontract notice periods are longer than those in the main contract, contractors may be liable for a delay they can no longer pass on.
3. Rising costs: hardship and price adjustment clauses
For price increases, the suitable tool in Romanian construction contracts is hardship (“impreviziune”) under Article 1271 of the Civil Code. A court may adapt or terminate the contract if performance has become excessively onerous because of an exceptional change of circumstances, provided that: (i) the change occurred after signing; (ii) neither the change nor its extent could reasonably have been foreseen; (iii) the debtor did not assume the risk; and (iv) the debtor tried, within a reasonable time and in good faith, to negotiate an adaptation of the contract.
Two practical consequences follow. First, a fixed-price clause in an EPC contract will be used against the contractor as evidence that it assumed the risk; the contractor’s pricing premium for that risk is part of the bargain. Second, the fourth condition (renegotiation attempt) is within the contractor’s control: it must send a reasoned, documented renegotiation request as soon as possible, with supporting invoices and quotations, rather than after the loss has crystallised.
In public works contracts, Law no. 98/2016 (Article 221 et seq.) allows price adjustment only through clear and precise clauses included in the tender documents, which the contracting authority must include for works contracts lasting more than six months (Article 2222(9) of Law no. 98/2016). The temporary relief schemes adopted after earlier shocks (Government Ordinance no. 15/2021, Emergency Ordinances nos. 47/2022 and 64/2022) should not be assumed to apply again unless a new act is adopted – especially in the context of the current budgetary constraints in Romania. Therefore, where a price adjustment clause exists, it must be invoked promptly; where it is missing from long-running public tender documentation, challenging the tender documentation should be considered.
4. Delay, extensions of time and liquidated damages
The default position is that delay falls on the contractor unless it proves an entitlement to an EOT. Delays caused by the employer generally justify relief, whereas “neutral” delays require an express contractual ground. Strict notice and condition-precedent regimes are likely to be scrutinised by Romanian courts against good faith (Article 1170 of the Civil Code), so contractors must be extremely dilligent in observing contractual deadlines.
Employers must be equally disciplined. LDs may depend on compliance with contractual preconditions (such as issuing a non-completion certificate), and under Romanian law a manifestly excessive penalty may be reduced by the court (Article 1541 of the Civil Code).
Another important point in the context of construction contracts in Romania is considering the debt recovery strategy. If the employer is a contracting authority, the contractor must consider that debt recovery in Romania against public authorities is not a straightforward process; courts may be inclined to dismiss or suspend enforcement applications against public entities if the conditions for enforcement are not strictly observed.
5. What to do now: practical recommendations
- Send protective notices (force majeure, EOT, cost) now, reserving all rights, and update them periodically;
- Build the causation record: supplier correspondence, price quotations, invoices, shipping logs and a delay analysis against the baseline programme;
- Mitigate visibly: alternative suppliers, early purchase of key materials, re-sequencing of works, with costs recorded and approved in writing;
- Align the chain: back-to-back subcontract terms, shorter subcontract notice periods and pass-through of supplier force majeure notices;
- Propose interim agreements: indexation for named materials, open-book price sharing or extended offer validity;
- Review insurance (political risk, trade disruption, delay in start-up) and extend bonds and guarantees before they expire;
- Draw up a strategy for debt recovery in Romania: consider the employer’s assets, whether it is an SOE of strategic importance and check enforcement trends in the applicable local jurisdiction;
- Comply with multi-tier dispute clauses (DAB, Supervisor’s determination (GD No. 1/2018), mediation) before arbitration; ensure identical arbitration clauses across the contract chain to enable consolidation.
6. Arbitration: the most suitable dispute resolution method
Arbitration provides the best framework for litigating complex construction disputes in these uncertain times. It has the advantages of specialised independent arbitrators, speedy resolution compared to state court disputes and direct enforcement in more than 170 countries, by virtue of the New York Convention.
For specialist legal assistance in the performance of construction contracts and related disputes, we invite you to contact the Sarbu Partners team at office@sarbupartners.ro.